HENDERSON 2000

HENDERSON 2000 - Empire, Colo.

TIC was the general contractor for the installation of 10.5 miles of underground conveyor, 4.5 miles of above ground conveyor, and underground crusher installation. This was the world’s longest single-flight conveyance system at the time of installation.

Technical Details

  • A Fuller 54” x 84” crusher
  • 10,000 cy concrete
  • 2,500 tons of building steel
  • 708 tons of drive structural steel
  • 14,803 lf of pipe
  • 25,000 lf conduit
  • 32,770 ft of HV wire
  • 76,000 ft LV cable
  • 146,834 ft of instrument cable
  • 6,820 ft of cable tray
  • 84,000 ft of ground wire
Quick Links
Featured Projects
LA CYGNE GENERATING STATION
LA CYGNE GENERATING STATION
La Cygne, Kan.
Contact Kiewit

Home Office : 3555 Farnam St. Omaha, NE

Home Office : (402) 342-2052

General Info : [email protected]

Locations Page   |   Career Search

Featured Projects

LA CYGNE GENERATING STATION
LA CYGNE GENERATING STATION
La Cygne, Kan.

Contact TIC

Home Office :

10055 Trainstation Circle
Lone Tree, Colorado 80124
 

 

Office : 

720-920-4200

 

Jobs Hotline : 

833-281-5273

 

Locations Page   |   Careers